Compulsory acquisition

I received a Proposed Acquisition Notice

A Proposed Acquisition Notice (PAN) is the formal notice the acquiring authority gives before it compulsorily acquires your land under the Land Acquisition (Just Terms Compensation) Act 1991. It is not merely a negotiating letter. It begins a statutory pre-acquisition process with fixed timeframes, including a period for lodging a compensation claim. What you do after receiving it can materially affect negotiations, the evidence available and your ultimate compensation position.

Jurisdiction
New South Wales
Page type
Issue overview
Timing
Time-sensitive
On this page

This page may be relevant if:

  • You have received a document headed 'Proposed Acquisition Notice'
  • An authority has written to you about acquiring all or part of your land
  • You want to understand the deadlines the notice has started
  • You are deciding whether to negotiate, make representations or prepare your compensation claim

What this usually means

  • A PAN signals an authority's intention to acquire your land by compulsory process, and is given before the acquisition is finalised.
  • It begins a statutory pre-acquisition process with periods set by the Act or the notice, including a compensation-claim period of at least 60 days after the notice is given. Some periods can be shortened or extended under the Act.
  • A person who has claimed compensation may generally object to the amount offered in the Land and Environment Court within 90 days after receiving the compensation notice. If no compensation notice is given, a claim can still be lodged with the authority; a rejected claim, including one taken to be rejected after 60 days without a decision, may generally be appealed within 90 days after rejection. A late objection or appeal requires good cause.
  • Receiving a PAN does not stop you negotiating; many matters are still resolved by agreement on improved terms.

What commonly matters

  1. The compensation claim period

    The PAN requests an owner seeking compensation to lodge a claim within its specified period, which must be at least 60 days after the notice is given. A compensation claim can be lodged with the acquiring authority or the Valuer-General. Acquisition and assessment can proceed without a claim, but the right to object to the amount belongs to a person who has claimed compensation. Missing the PAN's claim period does not by itself extinguish the compensation entitlement; obtain advice promptly about the claim and any later objection deadline.

  2. Negotiation and validity challenges

    A PAN does not foreclose negotiation. A validity challenge is separate from compensation and is generally brought by judicial review in the Supreme Court. Judicial review of a decision generally must begin within three months under rule 59.10 of the Uniform Civil Procedure Rules 2005, subject to extension and the rule's exceptions. Seek advice promptly because interim relief may be needed before acquisition takes effect.

  3. What is actually being taken

    Whether the authority is taking the whole site, part of it, or an easement changes the impact on the rest of your land, and the compensation.

  4. Early evidence

    Valuation, disturbance and business-impact evidence gathered early shapes the claim that follows the acquisition.

How we help

  • Explain what the notice means and identify the pre-acquisition and compensation-claim deadlines it starts
  • Advise on negotiations, representations and preparation of your compensation claim
  • Advise on any later compensation notice and, where appropriate, prepare and run an objection in the Land and Environment Court
  • Coordinate valuation and disturbance evidence and frame your compensation claim

This page is general information only and is not legal advice. It may not be current, and how the law applies depends on the specific facts. For advice on your situation, contact Stone & Pillar Legal.

Frequently asked questions

General information only, not legal advice. The position depends on your circumstances.

What is the minimum notice period under a Proposed Acquisition Notice in NSW?

Under the Land Acquisition (Just Terms Compensation) Act 1991 (NSW), a Proposed Acquisition Notice generally must give at least 90 days before the acquisition can be completed by Gazette notice. The Act permits a shorter period in specified circumstances, including written agreement or the statutory Ministerial urgency process. A PAN is taken to be withdrawn if acquisition has not occurred within 120 days after it is given, unless a longer period is agreed in writing. After withdrawal, another PAN generally cannot be given within 12 months unless the Minister is satisfied that the circumstances justify it. The relevant notices, agreements and statutory exceptions should be checked promptly.

Can I stop the compulsory acquisition of my land after receiving a PAN?

A Proposed Acquisition Notice begins a statutory process, and in practice a landowner usually cannot prevent a properly authorised acquisition from proceeding. The notice period generally allows time to make representations to the authority and to negotiate over what is taken and the terms, while a challenge to the validity of an acquisition is a separate matter that would commonly be pursued by judicial review in the Supreme Court rather than through the compensation process. Whether any grounds to challenge exist depends on the facts and the authority's powers, so the specific notice should be reviewed promptly.

Who decides how much compensation I get when my land is compulsorily acquired in NSW?

After land is acquired under the Just Terms Act, the amount of compensation is initially determined by the Valuer-General, and the acquiring authority generally must give the former owner a compensation notice setting out the offer within 45 days of the acquisition notice being published (a period the Minister can extend in limited circumstances). A person who has claimed compensation and disagrees with the amount may generally lodge an objection with the Land and Environment Court within 90 days of receiving that notice, in the Court's Class 3 jurisdiction. The right to object belongs to a person who has claimed compensation, and a compensation notice can arrive before any claim has been made, so it is worth checking early that a claim has been lodged. The compensation payable depends on the facts, including valuation and disturbance, so the timeframes and the offer should be checked against the specific notice.

What happens if I do nothing after receiving a Proposed Acquisition Notice?

If no action is taken, the authority can generally proceed to acquire the land by publishing an acquisition notice in the Gazette once the notice period has run. If a later compensation offer is not accepted and no objection is lodged with the Land and Environment Court within the 90-day period, the right to object to the amount is generally lost (a late objection is only sometimes allowed for good cause) and compensation is generally fixed at the amount offered. Because these timeframes are short and strict, the position should be checked promptly against the specific notice.

Where to start

Received a notice? Talk it through

Tell us the acquiring authority, the type of notice, the date it bears and the date you received it. On a short preliminary call we can tell you whether we can assist and what the first step would be.

Request a call back

Speak with a lawyer

30 minutes · Phone or Teams · No charge

The complimentary 30-minute preliminary call is intended to discuss whether we can assist and what an initial scope of work would involve. It is not intended to provide legal advice. Ask us to confirm in writing the work we have agreed to undertake. Tell us any date stated in the documents. Do not assume that sending an enquiry or making a booking protects a deadline. Ask us to confirm the work we have agreed to undertake, including any action about a deadline. If a date is close or uncertain, seek prompt legal advice rather than waiting for an online reply.

Speak with a lawyer Call